DiaryAll the phases of restoring a 12-metre R-Yacht made of woodHere you can continually witness our restoration of the 12-metre R-Yacht yacht Anitra. You can keep up to date on all the details of the construction. Four year projectThe work has been underway since June 2003 and will last until about autumn 2006. The work has been divided into 15 construction groups, the current status of which we list here on a regular basis. On the following pages, you will find richly illustrated descriptions of the phases of restoration we have already passed through. We will update the diary quarterly with news. It is worth checking in regularly. Quality versus timePlease understand that we attach great importance to the quality of the pictures (as with our yachts) on the following pages. As a result, the loading times are slightly longer. If you click directly on any of the pages in the following list, it could result in a longer loading time. The enjoyment of viewing the individual pictures will be worth it. Kind regards, Josef Martin |
|
| History | |
| Date 2003 | Work description |
| January | |
| End of February | |
Last week of March | |
| June | Construction group 1: Clearing out the hull Electrical equipment, switch panels, displays, heating, hydraulic |
| June |
Deck - dismantling the superstructure and fittings |
| July |
Construction group 2: removing the ballast keel |
| July | |
| July | |
| July | Construction group 3: aligning the hull
|
| July | |
| End of July til September |
Construction group 4: Keel, stem, stern post, transom beam, transom |
| August | |
| August | |
| September | |
| September till December 2003 |
Construction group 5: Replacing the wooden frames Reconstruction of wooden frames Fitting the wooden frames into the keel section |
| Date 2004 | Work description |
| December till June |
Construction group 6: metal frames Steel frames - first impressions Steel frames in the keel section Preparations for replacing and repairing the steel frames Riveting the parts inside the hull |
| June 2004 till September 2005 |
Construction group 7: Planking |
| Date 2005 | Work description |
| October 2005 |
Construction group 8: Attaching the keel |
| October 2005 till the start of 2006 |
Construction group 9: Work on the deck |
| Date 2006 | Work description |